Pedestrian bridge lifted.

14.05.2017 – Last night, a temporary pedestrian and installation duct bridge was lifted and put in place at the station Harburger Bahnhof. For this, the rail tracks in the direction of Cuxhaven had been shut down for a 33 hour possession period.

The temporary bridge is needed because the irreparably damaged road bridge Hannoversche Straße is to be demolished at the beginning of 2018 and then to be renewed by the middle of 2019.

In the meantime, this temporary bridge will serve to route both the pedestrian traffic and the supply lines over the rail tracks of Deutsche Bahn.